A borrower with a 780 score, 20% down, and two years of clean tax returns can still lose a Florida condo contract — not because of their credit, but because the building fails. Conventional condo financing requires two separate approvals: one for the person, one for the project. Lenders underwrite the association's budget, its litigation history, its occupancy mix, and now, in Florida, its structural inspection record.
The second approval has become the harder one. Since the Surfside collapse in 2021, Florida has layered milestone inspections and structural integrity reserve studies onto a condo market that already carried heavy insurance costs. Lenders have responded by tightening project standards at the same time. That combination means the documents you request in the first week of a contract often decide whether the deal closes at all.
What follows is how the condo approval process actually works in Florida, what each requested document proves to an underwriter, and where the specific risks sit for buyers in Collier and Lee County and across the state.
Why does a condo need its own approval?
A condominium loan is secured by a unit inside a shared building, so the lender's collateral includes everything the association owns and everything the association owes. If the roof fails, the assessment lands on the unit owner — and a unit owner facing a large assessment is a unit owner at risk of default. Underwriters price that shared exposure through a separate project review.
The review answers three questions. Is the association financially sound enough to maintain the property? Is its legal structure compatible with mortgage lending? And does the physical condition of the building create a foreseeable bill that the budget cannot absorb? Fannie Mae's project standards FAQ lays out how lenders verify eligibility, including that sellers and servicers use Condo Project Manager to confirm whether a project holds Approved by Fannie Mae status (Fannie Mae).
That review is why a pre-approval letter is not the finish line. A borrower can be fully underwritten and still be told the project is ineligible, which in practice means switching loan programs, switching buildings, or losing the deal.
What documents does the lender actually request?
The document list is short but unforgiving, and every item exists to answer a specific underwriting question. Missing paperwork delays a closing; contradictory paperwork can end one. Here is what typically gets requested and what each item is proving.
The annual budget and current reserve balances. Shows whether monthly dues cover operating costs and whether money is actually being set aside for future repairs. Fannie Mae's project standards FAQ explains that the minimum annual budgeted replacement reserve allocation is calculated by dividing the reserve allocation by the association's annual budgeted assessment income (Fannie Mae).
Financial statements and the most recent reserve study. Establishes the association's real position, not the version summarized in a listing sheet. Where a reserve study is used to satisfy the reserve requirement, that same guidance states the highest recommendation must be used and that baseline funding methodology no longer qualifies (Fannie Mae).
The declaration, bylaws, and rules and regulations. Confirms the association can levy and collect assessments, that the lender's rights survive foreclosure, and that restrictions do not conflict with lending rules. Fannie Mae requires project documents to give a mortgagee written notice of casualty loss, assessment delinquency, insurance lapse, and condemnation (Fannie Mae).
The milestone structural inspection report. Documents the building's condition and any repair obligations the association has taken on.
Master insurance contact information and the current policy. Verifies coverage limits, deductibles, and who carries the risk of a casualty loss.
HOA management contact information. Needed because the questionnaire and any follow-up verification go through management, not the seller.
Two of these deserve more attention than they usually get in Florida. The insurance contact matters because a policy up for renewal, or one with a very high hurricane deductible, changes the association's real exposure. The inspection report matters because it is the one document that can convert a stable budget into a pending assessment.
What does the condo questionnaire actually ask?
The condo questionnaire is the document that translates a building's operations into the yes-or-no answers an underwriter can act on. It is completed by association management, not by the buyer or the agent, and the cost varies by association. Some manage it in-house for a nominal fee; others route it through a third-party vendor that charges for the review and any follow-up.
That detail matters to a closing timeline. The questionnaire is one of the few items on a loan file that the lender does not control, and a slow or unresponsive management company can stall a closing as effectively as a missing appraisal. In Southwest Florida, where seasonal staff turnover at management companies is common, asking who administers the questionnaire should happen before the contract date, not after.
The answers that carry the most weight:
Is there any pending litigation against the HOA? Litigation introduces an unknown liability, and most project reviews limit how much structural or construction-defect litigation a project can carry.
Are there any special assessments? If yes, what are they for? An approved assessment that the unit owner must pay is a future obligation the lender has to count, and an unfunded one signals a budget that cannot absorb the work.
Does any entity own more than 25% of the units? Heavy concentration in one owner means the association's decisions — and its financial health — depend on that owner's willingness to keep paying.
Are there any repairs related to health and safety or structural issues yet to be completed? This is the question Florida's new inspection regime made unavoidable. An inspection can identify work without the association having funded it. It is for this reason that it is now common to ask for the HOA meeting minutes for the last 12 months.
Answer any of these badly and the project review tightens. Answer several badly and the building becomes ineligible for the loan program the buyer was approved under.
Why do litigation, assessments, and ownership concentration carry so much weight?
Those four questionnaire items are not arbitrary. Each one measures a different way the association's costs can shift onto a single unit owner, and lenders treat a project's risk as a proxy for the borrower's.
Litigation turns the association's balance sheet into a question mark. A construction-defect suit may produce a recovery, but it may also consume years of assessments and delay repairs the building needs. Concentration works the other way: when one investor owns a large block of units, that owner's default — or its refusal to approve a needed assessment — can leave the remaining owners carrying the full cost of the building. A single owner holding more than 25% of units is the threshold most lenders use to flag the risk.
Special assessments are the most direct transmission channel. Florida law now permits associations to fund structural work through loans, lines of credit, or special assessments, subject to member approval (Coverage Classroom). That flexibility helps associations spread a large bill, but it does not make the bill smaller. It converts a lump sum into higher monthly dues or a loan payment that follows the unit, and the next buyer's lender will see it in the budget.
How did Florida's post-Surfside laws change condo financing?
Florida now requires condo and co-op buildings three habitable stories or taller to complete a milestone structural inspection by December 31 of the year the building turns 30, then every 10 years, under state statute — and a local building official may require the first inspection at 25 years where salt-water proximity warrants it (Coverage Classroom).
The second requirement carries the money. Associations must complete a structural integrity reserve study (SIRS) at least every 10 years, covering the roof, load-bearing structure, fire protection, plumbing, electrical, waterproofing and exterior painting, windows and exterior doors, plus any other item costing more than the statutory threshold (Coverage Classroom). The initial SIRS was generally due by December 31, 2025, and for budgets adopted on or after December 31, 2024, required structural reserves may not be waived or reduced (Mersco).
The no-waiver rule is what changed monthly dues across Florida. A board that had spent years deferring roof and waterproofing costs now has to fund that horizon on a schedule, and where the SIRS found work needing attention immediately, the answer was often an assessment on top of the higher fee. House Bill 913, effective in 2025, added flexibility — loans, lines of credit, pooled reserves, and a limited pause after a milestone inspection — but did not reduce the underlying obligations (Mersco).
For a buyer, the practical consequence is that two older buildings on the same street can now look identical on the outside and be priced very differently, because one funded its reserves and the other is catching up.
What should buyers and agents ask for before the inspection period ends?
The right time to interrogate a building is before your contingency expires. Treat the documents as a pre-purchase inspection of the association, not as paperwork to collect at closing.
Ask for the milestone inspection report in full, including whether Phase 2 testing was triggered, and for the SIRS itself rather than a summary. Request the current budget alongside actual reserve balances, so you can compare what the board planned to fund against what it has. Ask directly whether any special assessment is approved, proposed, or under discussion, and what it covers. Then ask the management company whether the association is pursuing litigation or defending it.
A building that cannot produce these documents has effectively answered your question. So has a listing sheet that advertises low monthly dues in a building with an inspection report full of open repair items — the low fee usually means the bill has not been folded into the budget yet.
One more thing worth confirming early: whether the project is on an approved list for the loan program you intend to use. Conventional and government-backed programs apply different project rules — Fannie Mae, for instance, accepts conventional loans in established projects on the FHA-approved condo list only when the FHA approval came through its HUD review process rather than a lender's own review (Fannie Mae). A building that fails one review is not necessarily ineligible everywhere.
Christi Moran | First Premier Mortgage | NMLS ID 2668389
After closing more than 200 condo loans, I’ve become a local resource for buyers and real estate agents navigating warrantable and non-warrantable condo financing in Southwest Florida. For a complimentary condo doc checklist or to see if a condo is already on the approved condo list, email christi@fpmortgage.com with the condo project name and zip code.